August 11, 2008


MODELS

Our tower models are nearly complete, with some minor clean-up and detailing left. Click each thumbnail below to enlarge.

  • Kitchen
  • Kitchen/Dining
  • Living Room
  • Bedroom
  • Laundry Area
  • Living Room
  • Living/Dining Room
  • Living Room/Bedroom
  • Kitchen
  • Living Room
 

COMMON AREAS

The garden deck is complete! Note the extensive landscaping and large copper water feature. The pool terrace has soil and dozens of shrubs, plants, and flowers ready to be planted, which we'll feature in an update later this week. The pool terrace is scheduled for completion on August 16. Click each thumbnail below to enlarge.

  • Pool Terrace Landscaping
  • Pool Terrace Landscaping
  • Pool Terrace Landscaping
  • Garden Deck Landscaping
  • Garden Deck Landscaping
  • Copper Water Feature - Garden Deck
 

EXTERIOR PROGRESS

Major detail and finish work is currently underway on the 2nd Street and Sierra Street exterior floors one through six. The brick facade is installed on the Sierra Street columns, and next week 2nd Street's large columns will have brick applied as well. Brick will also be installed on all of the interior balconies on floors two through six next week. Click each thumbnail below to enlarge.

  • Exterior Penthouse Windows
  • Overview
  • Welcome to Reno!
  • Southern Overview
  • Overview
  • Overview
  • Brick Facade
 

MAY 2006
AUGUST 2006
OCTOBER 2006
JANUARY 2007
MAY 2007
AUGUST 2007
JANUARY 2008
AUGUST 11, 2008
AUGUST 23, 2008